By Eric Schweibenz
On November 19, 2009, the International Trade Commission issued a notice deciding to extend the target date for completion of the investigation in Certain Variable Speed Wind Turbines and Components Thereof (Inv. No. 337-TA-641).

By way of background, and as explained in our October 8 post, the Complainant in this investigation is General Electric Co. and the Respondents are Mitsubishi Heavy Industries, Ltd., Mitsubishi Heavy Industries America, Inc., and Mitsubishi Power System, Inc.  On August 7, 2009, ALJ Carl C. Charneski issued an initial determination (“ID”) finding violation of Section 337.  On October 8, 2009, the Commission issued a notice determining to review the ID.

In the November 19 notice, the Commission “determined to extend the target date for completion of the investigation by eleven days to December 18, 2009.”