By Eric Schweibenz
Further to our
November 23 post, on December 18, 2009, the International Trade Commission issued a
notice deciding to further extend the target date for completion of the investigation in
Certain Variable Speed Wind Turbines and Components Thereof (Inv. No. 337-TA-641).
By way of background, the Complainant in this investigation is General Electric Co. and the Respondents are Mitsubishi Heavy Industries, Ltd., Mitsubishi Heavy Industries America, Inc., and Mitsubishi Power System, Inc. On August 7, 2009, ALJ Carl C. Charneski issued an initial determination (“ID”) finding violation of Section 337.
See our
October 29 post for more details. On October 8, 2009, the Commission issued a notice determining to review the ID.
See our
October 8 post for more details.
In the December 18 notice, the Commission “determined to extend the target date for completion of the investigation to January 8, 2010.”