Further to our May 28, 2010 post, on July 15, 2010, ALJ Theodore R. Essex issued Order No. 4:  Setting the Target Date and Date for Submission of Proposed Procedural Schedules in Certain Lighting Products (Inv. No. 337-TA-719).

According to the Order, ALJ Essex set October 3, 2011 as the target date (which is 16 months after institution of the investigation).  ALJ Essex further indicated that any final initial determination on violation should be filed no later than June 2, 2011.  In addition, ALJ Essex noted that the evidentiary hearing in this matter will commence on March 17, 2011.

The Order directs the parties to submit a proposed procedural schedule by no later than July 23, 2010.