12
Dec
By Eric Schweibenz
Further to our November 7, 2011 post, on November 29, 2011, ALJ David P. Shaw issued Order No. 6: Setting Procedural Schedule in Certain Integrated Solar Power Systems and Components Thereof (Inv. No. 337-TA-811).In the Order, ALJ Shaw included provisions for the early exchange of claim terms and proposed constructions. In addition, the evidentiary hearing is scheduled for September 24, 2012. The Initial Determination is due on January 8, 2013 and the target date for completing the investigation is May 8, 2013 (which is 18 months after institution of the investigation).